Office Fit-Out N.Sydney.

In 2010 I started a project that consisted of wiring a complete office from an empty shell. This office was going to be an IT Training office that required a lot of data cabling and the office space was about 1500 Sq meters and totally empty prior to the fit out. The space consisted of 6 Training classrooms, break out area, kitchen and reception.

All power points were wired for each PC in the training room along with each PC having its own data connection.

Each training room also had a plasma TV mounted to the wall and was wired to the trainers desk for presentations.

Lights and emergency lights were installed and switched accordingly to each training room.

This project was completed from start to finish in 10 working days and met the client time frame with no faults or defects.

     
     
     
     
     
     

     